Saturday, 21 November 2009

Structural Flooring (III)

The structural flooring is now almost covered with concrete. The builders will finish covering it as they start building the Termoarcilla block walls.











Wednesday, 18 November 2009

Another panoramic view



Sorry that it shows that small, but it's a 180º panorama!!! You´ll have to click on it if you want to see anything ;-)

Structural flooring (II)

All the Cupolex domes have already been installed, including pipes underneath, etc. They're now setting up the iron structure for the armed retainig wall. Once they've finished, by friday or so, they'll start pouring the concrete.

The'll fill it all with concrete and on top of it they'll start to build up the walls.